EE-EW Public Works Projects Update – October 2025
ENGLISH ESTATES – ENGLISH WOOD OVERVIEW MAP

CITY OF CASSELBERRY UTILITIES WATER MAIN REPLACEMENT
The above map is a general overview of the phasing of the City of Casselberry’s Water Main Replacement within English Estates / English Woods:
-
Installation of the water main is 99% complete, awaiting the result of BT Testing before making all final cutovers to the new water main distribution piping in Phase I.
-
Miscellaneous service connections are in the final process.
-
After all customers have their new service, the out-of-service AC pipe will be capped and filled with grout.
-
Major pavement restorations have been completed.
-
Phase II extension of replacement into Bel-Aire North is not currently scheduled to start until January 2026. The only impact on EE—EW will be the connection on Glastonberry Rd. north of Hunterfield Rd.
SEMINOLE COUNTY OXFORD ROAD SIDEWALK AND STORM WATER DRAINAGE, and City of Casselberry Utilities Water Main Replacement
​
The critical path appears to be running approximately one month behind schedule. There is additional coordination required because the contractor’s interface with the City of Casselberry’s Northgate Phase I project and concurrent construction locations. The contractor is planning to add a second crew within a week or two, with two separate construction locations.
​
Work on Oxford Rd will be proceeding north along the east side, under the existing sidewalk, placing the new water main, moving north toward the intersection of Hunterfield Rd. This will allow the existing underground utilities to adjust their existing facilities before construction of the new stormwater drainage. The contractor will be maintaining a traversable sidewalk of limestone and recycled asphalt until the new storm drainage and sidewalk can be constructed. Pedestrians can request assistance through the work zone during the period of activity. Dewatering equipment is required to keep the work area dry/accessible during the time. Pedestrians are requested to avoid the work area as much as possible.
The additional crew, when available, will be constructing the new water main on the south side of Derbyshire Rd. in both directions from Chipola Rd. As new water mains become available, new service will be scheduled.